An approved Zoning Clearance or Site Plan Review is valid for a period of 18 months from its effective date. A Minor Use Permit, Conditional Use Permit or Variance is valid for 24 months after its effective date. At the end of this time period, the land use permit shall expire and become void unless:
A.
Substantial site work toward establishing the authorized use has been performed (Section 22.64.080); or
B.
The project is completed (Section 22.64.090); or
C.
An extension has been granted (Section 22.64.070).
Nothing in this Title shall be construed as affecting any time limits established by Title 19 of this code regarding work authorized by a building permit or other construction permit issued in compliance with Title 19, or time limits relating to the expiration of the permit.
[Amended 1986, Ord. 2250] [22.02.040]