§ 23.02.021. Pre-application Conference.  


Latest version.
  • The applicant or his representative is encouraged to request a pre-application conference, subject to the applicable fee, with staff of the Department of Planning and Building as early in the process as possible (i.e., prior to any substantial investment such as land acquisition and site engineering and construction plans). During the conference, department representatives, and where applicable, representatives from other county departments, should discuss applicable policies, plans, standards, and requirements as they apply to the proposed project, review the appropriate procedures for processing the application and examine possible alternatives or modifications relating to the proposed project. Land use, land division and lot line adjustment applications are subject to a public hearing and are discretionary. Action on the application by the Review Authority may differ from the opinion given by staff during the pre-application conference.

[Added 1995, Ord. 2715]