§ 23.02.046. Occupancy or Use of Partially Completed Projects.
Multiple building projects (including but not limited to apartment or office complexes and shopping centers), may be granted Certificates of Occupancy for individual completed buildings in advance of completion of the entire project only when:
a.
Individual buildings are completed pursuant to Section 23.02.044 (Project Completion); and
b.
The Planning Director determines that the completed structures are capable of functioning independently from structures remaining to be completed; and
c.
Occupancy of individual structures will not inhibit the completion of the total project; and
d.
Partial occupancy during completion will not have a potential adverse effect on persons in the area or nearby properties.
e.
Occupancy with incomplete site improvements is accomplished pursuant to Section 23.02.048.