§ 23.08.318. Photovoltaic Generating Facilities.  


Latest version.
  • a.

    Application contents. In addition to the general requirements of Section 23.08.312(2), an application for a photovoltaic generating facility shall describe:

    (1)

    Tracking system design, including a showing that no concentrated reflections will be directed at occupied structures, recreation areas or roads.

    (2)

    How public access will be restricted or why public liability is not a concern at the particular facility.

    b.

    Undergrounding required. Electrical distribution lines on the project site shall be undergrounded up to the low voltage side of the step-up transformer, to the point of on-site use, or to the utility interface point of an on-site substation.

[Added 1992, Ord. 2591]